What action regarding vent lines is required for a UST in temporary closure?

Prepare for the A-B Operator Petro-Tech Exam. Utilize flashcards and multiple choice questions with hints and explanations. Ace your exam seamlessly!

Multiple Choice

What action regarding vent lines is required for a UST in temporary closure?

Explanation:
Vent lines must be left open and functioning during temporary closure. They relieve vapor pressure as temperatures change and prevent buildup inside the tank, reducing the risk of leaks or vapor hazards. Closing, capping, or removing vent lines would trap vapors and pressure, creating safety and regulatory problems.

Vent lines must be left open and functioning during temporary closure. They relieve vapor pressure as temperatures change and prevent buildup inside the tank, reducing the risk of leaks or vapor hazards. Closing, capping, or removing vent lines would trap vapors and pressure, creating safety and regulatory problems.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy